Casino Belgrade

Implementation planning and project management of the entire casino and dining area

The first casino section was completed only 12 weeks after the contract had been awarded.

Due to static measures and the demolition of concrete, the implementation into the existing building turned out to be rather challenging. Implementation planning, order, and execution were coordinated locally.

Details

  • Building
    Casino Belgrade
  • Client
    trustsix gebäudeausstatter gmbh
  • City/Country
    Belgrad/Serbia
  • Start
    2007
  • Completion
    2008
  • Gross floor area
    8911 m2
  • Overall project management
    trustsix gebäudeausstatter gmbh

>> You want to know more about our working methods, references, or partners?

Click contact to get in touch with us.

You want to take a look at more of our projects?

Design im Ausstellungsbereich – ein Anliegen von uns.

Settings saved
Data protection

This site uses cookies. Choose which cookies you want to allow. You cannot use this website without your consent for the required cookies.

Please note that we also provide cookies from US companies. If you agree to their setting, your personal data collected by the cookie will be sent to the USA, where you are not subject to a level of protection appropriate to EU data protection law, you only enjoy limited or no data protection rights and, in particular, the US government has access to this data can.

You can change your cookie settings at any time on the data protection page.

You are using an outdated browser. The website may not be displayed correctly. Close